Golden 24 hours principle
----all the responses should be done within 24 hours!
Step.1 订单 Order
Step.2 开模分析 DFMEA
Step.3 模具设计要求 Tooling BOM Form
Step.4 模具 2D 图纸 Tooling 2D Drawing
Step.5 开工通知单 Cutting Tooling Notice
Step.6 生产进度表 Weekly Report
Step.7 模具3D Tooling 3D drawing
Step.8 检测报告 Dimension Report of T1 sample
Step.9 箱麦 Packing Information
Step.10 走模光碟 CD
Step.11 顶出机构测试 3000 cycles testing for tooling ejecting system
Step.12 模具测试手册 Plastic Mould Operation Manual